RAD at Washington Elms

Renovation work at Washington Elms, planned as part of the RAD-initiated modernization project, includes replacement of the boiler plant, fire alarm system upgrades, as well as masonry restoration, landscaping, civil infrastructure and development-wide site improvements.

RAD Conversion Date: April 1, 2015
Construction Start: April 2015
Date of Completion: April 2017

Architect: ICON Architecture, Boston, MA
Contractor: Boston Building & Bridge Corporation, Milton, MA

Relocation: Resident relocation is not required for this construction project.

For general questions about the Washington Elms revitalization please contact Kyle Sullivan at 617-520-6239 or ksullivan@cambridge-housing.org.

For construction related questions please contact Chris Terramane at 617-520-6393 or cterramane@cambridge-housing.org or Rick Jegorow at 617-520-6385 or rjegorow@cambridge-housing.org.